Ahmedabad Bullet Train Station: Three New Platforms Ready Beneath It

Overview
Indian Railways has finished three new platforms at Ahmedabad railway station, allowing regular trains to run below the under-construction bullet train station. The Commissioner of Railway Safety has inspected the new lines, and passenger operations can begin after safety approval.
Key Highlights
- New platforms 10, 11 and 12 are complete.
- Broad Gauge lines 16, 17 and 18 were built for them.
- The Commissioner of Railway Safety has finished its inspection.
- Union Minister of State V Somanna reviewed the work on Sunday.
What Happened?
Indian Railways has completed three platforms at Ahmedabad railway station, numbered 10, 11 and 12. They will serve trains running below the Ahmedabad bullet train station, which is being built above them. Three new Broad Gauge lines, numbered 16, 17 and 18, serve these platforms.
The Commissioner of Railway Safety has inspected the new lines. Trains can start using them once safety approval and other formalities are done.
On Sunday, Union Minister of State for Railways V Somanna inspected both the station redevelopment and the bullet train station. Officials briefed him on construction, passenger facilities and plans.
Why Is It Important?
Platform 10 had been closed since July 2022 because of work on the Mumbai-Ahmedabad High-Speed Rail (MAHSR) project. Once the platforms open, they can handle Express, Vande Bharat, and local trains, which adds capacity at the station.
Impact and Implications
The Ahmedabad bullet train station will cover around 38,000 square metres and have two platforms. Its roof design is inspired by kites and its exterior by the latticework of Sidi Saiyad Masjid. Planned facilities include waiting lounges, restrooms, retail outlets, lifts and escalators. It will connect to the existing railway station and Kalupur Metro station.
Railways says the redevelopment will create an integrated transport hub. It includes a new station building, a passenger concourse, an elevated road and better entry and exit arrangements.
Two other projects are also under way. A new Broad Gauge bypass line, called Y-connectivity, links Asarva station and Sabarmati ‘A’ Cabin and has also been inspected. A fifth line is being developed between Ahmedabad station and Kankaria depot to increase capacity.
What Happens Next?
Passenger operations on the new platforms depend on safety approval. No opening date has been announced.